Rigging Up

The components of the drilling rig and all necessary equipment are moved onto the location with large, specially equipped trucks. The substructure of the rig is located and leveled over the main bore hole. (Click here to see a diagram.) The mast or derrick is raised over the substructure and the other equipment such as engines, pumpls, and rotating and hoisting equipment are aligned and connected. the drill pipe and drill collars are laid out on racks convenient to the rig floor so that they may be hoisted up when needed and connected to the drill bit or added to the drill string. Water and fuel tanks are filled. Additives for the drilling fluid (drilling mud) are stored on location. When all these matters have been atended to, the drilling contractor is ready to begin drilling operations (sud the well).

 

 